Back to projects

Conduct Facility Improvement Studies at 4 Wastewater Treatment Facilities across the city

London, Ontario

completeWastewaterCWWF
Federal contribution
$85,500
Federal share50%

of $171.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2017201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 3, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2016
  • Construction end2 months lateforecast Dec 20, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49330 in the federal list. How to read these figures.