Treatment Plant Energy Reduction With Turbo Blowers - Supply and Install
Federal contribution
$1.3M
$1,268,500
Federal share37%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201720182019
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 20, 2019(actual)
Against the original forecast
- Construction end3 weeks lateforecast Mar 1, 2019