Design and Construction of Flood Protection Measures at the Vauxhall Pollution Control Plant

London, Ontario

completeWastewaterCWWF
Federal contribution
$2.3M
$2,341,500
Federal share50%

of $4.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 20, 2017
ApprovedMar 27, 2018
2017201820192020
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 1, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 1, 2016
  • Construction end5 months lateforecast Oct 1, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49332 in the federal list. How to read these figures.