Purchase and Installation of Variable Frequency Drives at 4 Sanitary Pump Stations
Federal contribution
$289,213
Federal share44%
of $658.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2017201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Dec 1, 2016(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start2 months lateforecast Oct 1, 2016
- Construction end3 months lateforecast Dec 20, 2019
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49335 in the federal list. How to read these figures.