Purchase and Installation of Variable Frequency Drives at 4 Sanitary Pump Stations

London, Ontario

completeWastewaterCWWF
Federal contribution
$289,213
Federal share44%

of $658.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2017201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Dec 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Oct 1, 2016
  • Construction end3 months lateforecast Dec 20, 2019