Sewer Separation Program Acceleration -Design and Construction
Federal contribution
$4.9M
$4,936,234
Federal share48%
of $10.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Jun 6, 2017(actual)
- Construction end
- Oct 31, 2020(actual)
Against the original forecast
- Construction start8 months lateforecast Oct 1, 2016
- Construction end14 months earlyforecast Dec 31, 2021
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49338 in the federal list. How to read these figures.