Sewer Separation Program Acceleration -Design and Construction

London, Ontario

completeWastewaterCWWF
Federal contribution
$4.9M
$4,936,234
Federal share48%

of $10.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 6, 2017(actual)
Construction end
Oct 31, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 1, 2016
  • Construction end14 months earlyforecast Dec 31, 2021