Arva Water Pumping Station Optimization and Energy Efficiency - Planning Study

London, Ontario

completeDrinking WaterCWWF
Federal contribution
$91,254
Federal share50%

of $183.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 13, 2017(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast Oct 1, 2016
  • Construction end6 months lateforecast Mar 31, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49341 in the federal list. How to read these figures.