Trunk Watermains Syphons and Pipeline - Inspections and Condition Rating

London, Ontario

completeDrinking WaterCWWF
Federal contribution
$501,550
Federal share42%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 30, 2017(actual)
Construction end
Jun 30, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Oct 1, 2016
  • Construction end3 months lateforecast Mar 31, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49342 in the federal list. How to read these figures.