Trunk Watermain Cathodic Protection Upgrades - Design and Construction
Federal contribution
$115,643
Federal share39%
of $295.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Apr 15, 2019(actual)
- Construction end
- Feb 28, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Feb 13, 2018
- Construction end5 weeks earlyforecast Mar 31, 2020
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49343 in the federal list. How to read these figures.