Watermain Cleaning and Relining - Design and Construction
Federal contribution
$526,500
Federal share50%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Mar 27, 2018(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start18 months lateforecast Oct 1, 2016
- Construction end5 months earlyforecast Mar 31, 2019