Back to projects

Watermain Cleaning and Relining - Design and Construction

London, Ontario

completeDrinking WaterCWWF
Federal contribution
$526,500
Federal share50%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Mar 27, 2018(actual)
Construction end
Oct 31, 2018(actual)

Against the original forecast

  • Construction start18 months lateforecast Oct 1, 2016
  • Construction end5 months earlyforecast Mar 31, 2019

Also in London

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49344 in the federal list. How to read these figures.