Cathodic Protection Program - Inspection, Design and Construction
Federal contribution
$190,213
Federal share37%
of $509.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Oct 31, 2017(actual)
- Construction end
- Aug 31, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Oct 1, 2016
- Construction end2 months earlyforecast Oct 31, 2019
Also in London