Cathodic Protection Program - Inspection, Design and Construction

London, Ontario

completeDrinking WaterCWWF
Federal contribution
$190,213
Federal share37%

of $509.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 31, 2017(actual)
Construction end
Aug 31, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Oct 1, 2016
  • Construction end2 months earlyforecast Oct 31, 2019

Also in London