Replacement of Main Street Watermains
Federal contribution
$25,000
Federal share50%
of $50.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of West Nipissing
- Construction start
- Oct 1, 2018(actual)
- Construction end
- Sep 17, 2019(actual)
Against the original forecast
- Construction start17 months lateforecast May 1, 2017
- Construction end14 months lateforecast Jul 31, 2018
Also in West Nipissing
- Installation of Sturgeon Falls Water Main Trunk Loop$2.0M
- Replacement of Complex Roof HVAC$152.3K
- Structural upgrade to wastewater forcemain at Holditch Street extension$150.0K
- Structural upgrade of Sand Hill area water services$125.0K
- Upgrade of brick manholes in numerous locations throughout Sturgeon Falls$121.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49570 in the federal list. How to read these figures.