Upgrade of brick manholes in numerous locations throughout Sturgeon Falls
Federal contribution
$121,876
Federal share49%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedFeb 26, 2018
2018
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of West Nipissing
- Construction start
- May 15, 2017(actual)
- Construction end
- Oct 31, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2017
- Construction end4 months lateforecast Jun 30, 2018