Back to projects

Structural upgrade to wastewater forcemain at Holditch Street extension

West Nipissing, Ontario

completeWastewaterCWWF
Federal contribution
$150,000
Federal share43%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Apr 27, 2018(actual)
Construction end
Oct 31, 2019(actual)

Against the original forecast

  • Construction start12 months lateforecast May 1, 2017
  • Construction end4 months lateforecast Jun 30, 2019

Also in West Nipissing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49662 in the federal list. How to read these figures.