Back to projects

Structural upgrade of Sand Hill area water services

West Nipissing, Ontario

completeDrinking WaterCWWF
Federal contribution
$125,000
Federal share50%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 20, 2018(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start14 months lateforecast May 1, 2017
  • Construction end21 months lateforecast Dec 31, 2017

Also in West Nipissing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49573 in the federal list. How to read these figures.