Replacement of two well pumps at the Crysler Well Heads
Federal contribution
$6,250
Federal share50%
of $12.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Aug 18, 2017(actual)
- Construction end
- Jun 30, 2019(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end3 months earlyforecast Sep 30, 2019
Also in North Stormont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49629 in the federal list. How to read these figures.