Back to projects

Rehabilitation of key infrastructure including the chlorine analyzer distribution systen and generator at the Crysler Sewage Pumping Station

North Stormont, Ontario

completeWastewaterCWWF
Federal contribution
$10,750
Federal share50%

of $21.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of North Stormont
Construction start
Aug 23, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017

Also in North Stormont