Rehabilitation of key infrastructure including the chlorine analyzer distribution systen and generator at the Crysler Sewage Pumping Station
Federal contribution
$10,750
Federal share50%
of $21.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Aug 23, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017