Replacement of two sewage pumps at Pumping Station #4 for the village of Finch
Federal contribution
$1,847
Federal share31%
of $6.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start12 months earlyforecast Apr 1, 2017
- Construction end6 months lateforecast Sep 30, 2017
Also in North Stormont