Replacing infrastructure including flow meter and unit heaters at Pumping Station # 1
Federal contribution
$8,000
Federal share50%
of $16.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Apr 11, 2018(actual)
- Construction end
- Dec 9, 2019(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2017
- Construction end4 months earlyforecast Mar 31, 2020
Also in North Stormont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49636 in the federal list. How to read these figures.