Replacement of sewage pump at pumping station #3
Federal contribution
$924
Federal share31%
of $3.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of North Stormont
- Construction start
- Apr 1, 2016(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start12 months earlyforecast Apr 1, 2017
- Construction end6 months lateforecast Sep 30, 2017
Also in North Stormont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49637 in the federal list. How to read these figures.