Back to projects

Replacement of sewage pump at pumping station #3

North Stormont, Ontario

completeWastewaterCWWF
Federal contribution
$924
Federal share31%

of $3.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of North Stormont
Construction start
Apr 1, 2016(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start12 months earlyforecast Apr 1, 2017
  • Construction end6 months lateforecast Sep 30, 2017

Also in North Stormont

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49637 in the federal list. How to read these figures.