Minden Hills Ultra Violet (UV) WasteWater Treatment System
Federal contribution
$50,000
Federal share44%
of $112.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Minden Hills
- Construction start
- Jun 30, 2018(actual)
- Construction end
- May 20, 2020(actual)
Against the original forecast
- Construction start13 months lateforecast Jun 5, 2017
- Construction end5 months lateforecast Dec 31, 2019
Also in Minden Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49659 in the federal list. How to read these figures.