Sludge Thickening Planning

Taylor, British Columbia

completeWastewaterCWWF
Federal contribution
$15,099
Federal share50%

of $30.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
District of Taylor
Construction start
Oct 10, 2017(actual)
Construction end
Feb 28, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017