Merrill Crescent Community Septic Field System Replacement

Sunshine Coast, British Columbia

completeWastewaterCWWF
Federal contribution
$32,500
Federal share50%

of $65.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
20182019
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 21, 2017(actual)
Construction end
Jan 21, 2019(actual)

Against the original forecast

  • Construction start12 months earlyforecast Dec 3, 2018
  • Construction end4 weeks earlyforecast Feb 15, 2019