Enilda water reservoir
Federal contribution
$360,000
Federal share50%
of $720.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2017
201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- County of Big Lakes
- Construction start
- Jun 6, 2018(actual)
- Construction end
- Jan 28, 2020(actual)
Against the original forecast
- Construction start3 weeks lateforecast May 15, 2018
- Construction end4 months lateforecast Sep 30, 2019