Back to projects

Enilda water reservoir

Big Lakes, Alberta

completeDrinking WaterCWWF
Federal contribution
$360,000
Federal share50%

of $720.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
County of Big Lakes
Construction start
Jun 6, 2018(actual)
Construction end
Jan 28, 2020(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 15, 2018
  • Construction end4 months lateforecast Sep 30, 2019

Also in Big Lakes