Water Treatment Plant Condition Analysis/Report to determine New Build/Rehabilitation Options
Federal contribution
$24,756
Federal share35%
of $70.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the City of Dryden
- Construction start
- Nov 22, 2017(actual)
- Construction end
- Apr 12, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Mar 31, 2017
- Construction end3 months lateforecast Dec 29, 2017
Also in Dryden