Back to projects

Water Treatment Plant Condition Analysis/Report to determine New Build/Rehabilitation Options

Dryden, Ontario

completeDrinking WaterCWWF
Federal contribution
$24,756
Federal share35%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 22, 2017(actual)
Construction end
Apr 12, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Mar 31, 2017
  • Construction end3 months lateforecast Dec 29, 2017

Also in Dryden