completeDrinking WaterCWWF
Federal contribution
$10,601
Federal share27%

of $40.0K total eligible cost; the rest comes from other partners.

Program
Clean Water and Wastewater Fund
Construction start
Apr 21, 2017(actual)
Construction end
Jun 30, 2017(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Mar 31, 2017
  • Construction end4 months earlyforecast Oct 31, 2017