Structural Relining (Cure in Place) of Sanitary Sewers at 4 locations

Dryden, Ontario

completeWastewaterCWWF
Federal contribution
$183,317
Federal share43%

of $425.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2017(actual)
Construction end
Jun 14, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast May 15, 2017
  • Construction end5 months lateforecast Dec 29, 2017

Also in Dryden

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50110 in the federal list. How to read these figures.