Study of Hawkesbury Water Filtration plant
Federal contribution
$46,582
Federal share27%
of $171.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Hawkesbury
- Construction start
- Jul 26, 2017(actual)
- Construction end
- Jun 10, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast May 15, 2017
- Construction end8 weeks earlyforecast Aug 2, 2019
Also in Hawkesbury
- Upgrade of the Hawkesbury Wastewater Treatment Plant$11.9M
- Hawkesbury Water Treatment Plant Clarifier Upgrades$1.1M
- Replacement of 550 meters of water main with new 200mm conduit and replacement of all lateral services$550.0K
- Installation of a 250mm diameter water main on Bon Pasteur Street between McGill Street and Geneviève Street$287.5K
- Robert Hartley Sports Complex COVID Improvements$140.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50126 in the federal list. How to read these figures.