Install Supervisory Control And Data Acquisition at 2 separate sewage pump station. Flow monitoring equipment at 19 sewage pumping stations. Light Emitting Diode at various sewage pumping stations.

LaSalle, Ontario

completeWastewaterCWWF
Federal contribution
$86,136
Federal share48%

of $180.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of LaSalle
Construction start
Sep 19, 2017(actual)
Construction end
Jul 20, 2018(actual)

Against the original forecast

  • Construction start8 months lateforecast Feb 1, 2017
  • Construction end5 months lateforecast Feb 28, 2018

Also in LaSalle

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50159 in the federal list. How to read these figures.