Installation of Mechanical Controlled bar screen at main sewage pumping station

LaSalle, Ontario

completeWastewaterCWWF
Federal contribution
$625,000
Federal share50%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201820192020
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of LaSalle
Construction start
Oct 1, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Feb 1, 2017
  • Construction end8 weeks lateforecast Dec 31, 2019