Dedicated emergency back up power supply for the sewage pumping stations.
Federal contribution
$44,328
Federal share46%
of $97.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of LaSalle
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Dec 19, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Feb 1, 2017
- Construction end9 months lateforecast Mar 31, 2018
Also in LaSalle
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50161 in the federal list. How to read these figures.