Dedicated emergency back up power supply for the sewage pumping stations.

LaSalle, Ontario

completeWastewaterCWWF
Federal contribution
$44,328
Federal share46%

of $97.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of LaSalle
Construction start
Jul 1, 2017(actual)
Construction end
Dec 19, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Feb 1, 2017
  • Construction end9 months lateforecast Mar 31, 2018