Separation of sewers on Lorne/Gladstone/Melrose/Henry/William Avenues

Leamington, Ontario

completeWastewaterCWWF
Federal contribution
$100,000
Federal share50%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2017
ApprovedMar 27, 2018
20172018201920202021
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Leamington
Construction start
Dec 1, 2016(actual)
Construction end
Nov 16, 2020(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Nov 15, 2016
  • Construction end10 months earlyforecast Sep 30, 2021