Back to projects

Separation of sewers on Parkdale and Coronation that serve 56 homes

Leamington, Ontario

completeWastewaterCWWF
Federal contribution
$431,000
Federal share50%

of $862.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2017
ApprovedMar 27, 2018
20172018
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Leamington
Construction start
Dec 1, 2016(actual)
Construction end
Dec 4, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Nov 15, 2016
  • Construction end2.3 years earlyforecast Mar 31, 2020

Also in Leamington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50164 in the federal list. How to read these figures.