Engineering Design for the Replacement of Watermains along Main Street between Charlotte Street and Parkhouse Drive
Federal contribution
$15,136
Federal share50%
of $30.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2017
201820192020
Built
Approved 7 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Southwest Middlesex
- Construction start
- Jan 2, 2018(actual)
- Construction end
- Dec 1, 2019(actual)
Against the original forecast
- Construction end5 months lateforecast Jun 30, 2019
Also in Southwest Middlesex
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51190 in the federal list. How to read these figures.