Altona / Rhineland Waste Disposal Ground Expansion

Altona, Manitoba

completeSolid Waste ManagementSCF
Federal contribution
$50,000
Federal share33%

of $150.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2017
2018
Built

Approved 4 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Altona
Construction start
Aug 28, 2018(actual)
Construction end
Dec 6, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 31, 2018
  • Construction end5 weeks lateforecast Oct 31, 2018