Altona / Rhineland Waste Disposal Ground Expansion
Federal contribution
$50,000
Federal share33%
of $150.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 9, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Altona
- Construction start
- Aug 28, 2018(actual)
- Construction end
- Dec 6, 2018(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 31, 2018
- Construction end5 weeks lateforecast Oct 31, 2018
Also in Altona
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51560 in the federal list. How to read these figures.