Back to projects

Inclusive Park

Paradise, Newfoundland and Labrador

completeRecreationSCF
Federal contribution
$206,807
Federal share11%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Easter Seals
Construction start
Jun 1, 2018(actual)
Construction end
Jun 14, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2018
  • Construction end2.4 years earlyforecast Oct 31, 2020

Also in Paradise

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51561 in the federal list. How to read these figures.