Storm Sewer - Midland Row East
Pasadena, Newfoundland and Labrador
Federal contribution
$306,757
Federal share32%
of $957.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2017
20182019
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Pasadena
- Construction start
- May 31, 2018(actual)
- Construction end
- Sep 15, 2019(actual)
Against the original forecast
- Construction start11 months earlyforecast May 6, 2019
- Construction end7 weeks earlyforecast Oct 31, 2019
Also in Pasadena
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51600 in the federal list. How to read these figures.