Lift Station Retrofit - Port au Bras Lift Station

Burin, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$57,169
Federal share18%

of $317.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 1, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Burin
Construction start
Nov 23, 2018(actual)
Construction end
May 31, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 16, 2018
  • Construction end17 months earlyforecast Oct 31, 2020

Also in Burin

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51614 in the federal list. How to read these figures.