Water/Sewer Upgrades for Cormack Drive Phase III
Clarenville, Newfoundland and Labrador
Federal contribution
$357,533
Federal share50%
of $716.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
20182019
Built
Approved 23 months before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Clarenville
- Construction start
- May 21, 2019(actual)
- Construction end
- Nov 8, 2019(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 30, 2018
- Construction end5 months earlyforecast Mar 31, 2020