Southwest Leamington Storm Water Management Pond and Outlet Environmental Study and Design

Leamington, Ontario

completeWastewaterCWWF
Federal contribution
$87,500
Federal share50%

of $175.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 27, 2018
20192020
Built

Approved 4 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Leamington
Construction start
Jun 25, 2019(actual)
Construction end
Nov 16, 2020(actual)

Against the original forecast

  • Construction start14 months lateforecast Apr 15, 2018
  • Construction end10 months earlyforecast Sep 30, 2021

Also in Leamington

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52136 in the federal list. How to read these figures.