Southwest Leamington Storm Water Management Pond and Outlet Environmental Study and Design
Federal contribution
$87,500
Federal share50%
of $175.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
20192020
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Leamington
- Construction start
- Jun 25, 2019(actual)
- Construction end
- Nov 16, 2020(actual)
Against the original forecast
- Construction start14 months lateforecast Apr 15, 2018
- Construction end10 months earlyforecast Sep 30, 2021
Also in Leamington
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52136 in the federal list. How to read these figures.