Newtown Road Booster Pump System Upgrade
Bishop's Falls, Newfoundland and Labrador
Federal contribution
$48,519
Federal share25%
of $190.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
2019
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Bishops Falls
- Construction start
- Sep 24, 2019(actual)
- Construction end
- Oct 31, 2019(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 15, 2019
- Construction end6 weeks earlyforecast Dec 15, 2019
Also in Bishop's Falls
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52197 in the federal list. How to read these figures.