Aeration System Upgrade - Lagoon 1

St. George, New Brunswick

completeWastewaterCWWF
Federal contribution
$82,565
Federal share49%

of $167.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
201920202021
Built

Approved 17 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of St. George
Construction start
Oct 13, 2020(actual)
Construction end
Nov 27, 2020(actual)

Against the original forecast

  • Construction start11 months lateforecast Nov 18, 2019
  • Construction end9 months lateforecast Feb 28, 2020