Pump house Treatment Plant Flow meter
Federal contribution
$8,000
Federal share50%
of $16.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2018
2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Cobalt
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Nov 19, 2018(actual)
Against the original forecast
- Construction start5 months earlyforecast Feb 15, 2018
- Construction end8 months lateforecast Mar 15, 2018
Also in Cobalt
- Install a chlorine analyzer loop for proven contact time in distribution$50.0K
- Energy Retrofit Municipal Buildings$31.3K
- Teck-Cominco Prospect Park Upgrades$23.9K
- Pumphouse Road Water Treatment Plant Backwash and Progress Valves replacement$20.0K
- Pumphouse Road Water Treatment Plant Chlorination system replacement$11.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52447 in the federal list. How to read these figures.