New Water Storage Tank - Port au Choix
Port au Choix, Newfoundland and Labrador
Federal contribution
$529,315
Federal share35%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2019
20202021
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port aux Choix
- Construction start
- Oct 15, 2019(actual)
- Construction end
- May 27, 2021(actual)
Against the original forecast
- Construction start3 months earlyforecast Jan 1, 2020
- Construction end7 months earlyforecast Dec 17, 2021
Also in Port au Choix