New Water Storage Tank - Port au Choix

Port au Choix, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$529,315
Federal share35%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port aux Choix
Construction start
Oct 15, 2019(actual)
Construction end
May 27, 2021(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jan 1, 2020
  • Construction end7 months earlyforecast Dec 17, 2021