Town Pumphouse Upgrades
Port au Choix, Newfoundland and Labrador
Federal contribution
$113,476
Federal share40%
of $283.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port aux Choix
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Nov 25, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 3, 2022
- Construction end3 weeks earlyforecast Dec 15, 2022