Upgrading Lift Station #4
Port au Choix, Newfoundland and Labrador
Federal contribution
$96,841
Federal share40%
of $242.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.2 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Port aux Choix
- Construction start
- Sep 18, 2023(actual)
- Construction end
- Sep 4, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast May 2, 2023
- Construction end9 months lateforecast Dec 15, 2023
Also in Port au Choix
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65405 in the federal list. How to read these figures.