New Sidewalks Various Road Locations

Port au Choix, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$236,438
Federal share33%

of $709.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2024
20242025
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Port aux Choix
Construction start
Sep 16, 2025(actual)
Construction end
Nov 14, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast May 19, 2025
  • Construction end2 weeks lateforecast Oct 31, 2025