Lift Station #4 Upgrades

Port au Choix, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$82,984
Federal share40%

of $207.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
BuiltForecast

Approved 21 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Port aux Choix
Construction start
Aug 25, 2025(actual)
Construction end
Oct 31, 2025(forecast)

Against the original forecast

  • Construction start7 months lateforecast Jan 13, 2025