Municipality of the County of Colchester - Wastewater Collection Improvements: Valley, Salmon River, Debert

Colchester, Nova Scotia

completeWastewaterGIS
Federal contribution
$673,480
Federal share36%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
202020212022202320242025
Built

Approved 5 weeks before the announcement.

Program
Green Infrastructure Stream
Construction start
May 19, 2020(actual)
Construction end
Feb 20, 2025(actual)

Against the original forecast

  • Construction start3 months lateforecast Feb 17, 2020
  • Construction end6 weeks earlyforecast Mar 31, 2025