Paradise Road Upgrading - Archibald Drive to St. Thomas Line

Paradise, Newfoundland and Labrador

completeHighways and RoadsRNIS
Federal contribution
$821,345
Federal share33%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
20202021
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Paradise
Construction start
Sep 1, 2020(actual)
Construction end
Nov 15, 2021(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 10, 2020
  • Construction end9 months earlyforecast Aug 31, 2022

Also in Paradise

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 54339 in the federal list. How to read these figures.