City of Port Colborne Nickel Beach Bike Lane

Port Colborne, Ontario

underwayActive TransportationPTIS
Federal contribution
$195,168
Federal share40%

of $487.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 25, 2020
202120222023202420252026
BuiltForecast

Approved 8 weeks before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of Port Colborne
Construction start
Sep 15, 2025(actual)
Construction end
Apr 1, 2026(forecast)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2025

Also in Port Colborne