City of Port Colborne Nickel Beach Bike Lane
Federal contribution
$195,168
Federal share40%
of $487.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 25, 2020
202120222023202420252026
BuiltForecast
Approved 8 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Port Colborne
- Construction start
- Sep 15, 2025(actual)
- Construction end
- Apr 1, 2026(forecast)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2025
Also in Port Colborne
- Seaway Wastewater Treatment Plant Expansion$7.2M
- Construction of a Multi-Use Health and Wellness Recreation Centre$6.9M
- Watermain Replacement in Port Colborne$2.0M
- Highway 140 - Highway 3 to Niagara Road 23 in Port Colborne$1.5M
- Replacement of 340 meters watermain and 290 meters of sanitary sewers on Janet Street including storm sewer repair, as needed$361.7K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 55179 in the federal list. How to read these figures.